Site Usage

Step 1

Preparation ... Step 1

Excavate for below plinth work

step 2

Preparation ... Step 2

Complete foundation & plinth work. Aluminum Forms can be used for foundation and plinth works

Step 4

Process … Step 4

Set up the ceiling forms

step 4

Step 5

Process … Step 5

Slab, electrical & plumbing in slab

step 6

Process … Step 6

Pour concrete for walls & slab together (monolithic)

Step 7

Process … Step 7

Strip the wall forms (next day). Ceiling Forms to be stripped as per structural requirement.

step 7

Process … Prepare for next pour

Clean the forms for the next reuse
- Clean the face, the side rails, the top rails and the back immediately after stripping
- This improves the finish of the concrete and increases the life of the form

Process

Process ...

Move to the next level (2 to 3 day cycle time)

Result

Result …

Light weight forms allow high productivity

Safety

  • Ensure all scaffold brackets are in good condition and have not been damaged since the last installation
  • Ensue platform is fully decked out and toe-board and handrail installed.
  • Penetration holes in the slab for transferring panels must be covered when not in use until cast with correct.
  • Any workers working above platform level must wear safety belt attached to a secured formwork component or the wall steel.
  • When removing of the timber batons from the floor after casting ensure no nails have been left exposed.
  • Pins and wedges to be removed with care especially on the external of the building.
  • Handling of equipment.
  • Formwork should not be stacked on the scaffold.

Post – Concrete Activities

  1. Strike Wall Form- It is required to strike down the wall form.
  2. Strike Deck Form- The deck form is then removed.
  3. Clean, Transport and stack formwork
  4. Strike Kicker Formwork – The kicker are removed.
  5. Strike wall – Mounted on a Working Platform the wall are fitted on next floor.
  6. Erect Wall – Mount Working Platform and the wall is erected.
Normally all formwork can be struck after 12 hours.